SHADOW LOGISTICS AND INFRASTRUCTURE MINISTER — DAY 2: TREASURER BREAKS HIS WORD ON INFRASTRUCTURE WITHIN A YEAR
Thursday, 11 June 2026
In his first Budget Speech, Treasurer Bill Yan set his own test for the Finocchiaro CLP Government. He promised Territorians that under the CLP, projects would be delivered on time, on budget and with integrity.
Less than a year later, Bill Yan has walked away from his own words.
At Estimates yesterday, he would not give the same guarantee he gave in his first Budget Speech.
The CLP came to Government telling Territorians they would fix infrastructure delivery. Instead, projects are slipping, communities are waiting longer, and the Treasurer will not even stand by the standard he set for himself.
- Alice Springs new library, delayed by 12 months, from Q1 2026 to Q1 2027.
- Peter McAulay Centre Joint Emergency Services Communications Centre upgrades, delayed by 15 months, from Q1 2026 to Q2 2027.
- Centralian Senior College air conditioning upgrade, delayed by 12 months, from Q3 2025 to Q3 2026.
- Alice Springs new multicultural centre, delayed by 9 months, from Q4 2025 to Q3 2026.
- Sandover Highway upgrade to seal standard, delayed by 9 months, from Q4 2025 to Q3 2026.
These are projects communities were told would be delivered, now they are being pushed back under a government that promised the opposite.
Worse still, Bill Yan refused to guarantee that project scopes would not be cut to squeeze projects back within budget.
That means Territorians could be waiting longer for projects that may deliver less than they were promised.